Provided by Virginia Department of Transportation (VDOT)
Drivers should expect nightly lane closures for paving work on I-66. Work hours may include extended evening and morning hours in the non-peak commute direction between Route 234 Business (Sudley Road) and Route 29 in Centreville. Closures will happen this week and continue through October. Double lane closures on I-66 East on weekdays will begin as early as 7:00 p.m. and continue until as late as 5:00 a.m. to accommodate the work. Double lane closures on I-66 West on weekdays will begin as early as 9:00 p.m. and continue until as late as 10:00 a.m. Drivers should plan ahead to avoid construction delays.
Details of planned work includes:
I-66 East from Route 234 Business to Route 29 Centreville
- Sunday: 9:00 p.m. to 5:00 a.m.
- Monday through Thursday: 7:00 p.m. to 5:00 a.m.
- Friday and Saturday: 10:00 p.m. to 8:00 a.m.
I-66 West from Route 29 Centreville to Route 234 Business
- Sunday through Thursday: 9:00 p.m. to 10:00 a.m.
- Friday and Saturday: 10:00 p.m. to 8:00 a.m.
Work on I-66 West will progress from east to west. Work on I-66 East will progress from west to east. Crews will generally mill and pave one lane each night.
Work hours are subject to change based on weather, traffic, and other factors. Weekly schedule updates will be available at Transform66.org and on VDOT’s Twitter @VaDOTNOVA. To receive updates automatically by email, sign up here.
When complete, the Transform 66 Outside the Beltway Project will feature three general purpose and two Express Lanes in each direction from I-495/Capital Beltway to Route 29 in Gainesville. The I-66 Outside the Beltway Express Lanes are expected to open in December 2022.