Featherstone Road, Blackburn Road Nighttime Paving to Continue week of October 3-7

Google+ Pinterest LinkedIn Tumblr +

Provided by Virginia Department of Transportation (VDOT)

featherstone-paving-map

UPDATE: Please note the nighttime paving on Featherstone Road and Blackburn Road will continue on the following dates:

-Monday, October 3 through Thursday, October 6: 9:00 p. m. to 5:00 a. m.
-Friday, October 7: 9:00 p. m. to 9:00 a. m.

Lane closures for milling and paving will occur nightly on portions of Featherstone Road and Blackburn Road from 9:00 p. m. to 5:00 a. m. Monday, September 19 through Thursday, September 22, and from 9:00 p. m. to 9:00 a.am. Friday, September 23, according to the Virginia Department of Transportation.

Featherstone Road will be paved between Blackburn Road and the railroad crossing, and Blackburn Road will be paved between Featherstone Road and Wentwood Lane.

Motorists can expect delays and are advised to use alternate routes.

Some of this work will occur close to residential areas, with the potential for loud noise. VDOT appreciates residents’ patience as we work to complete this needed work on busy roads at night.

Follow VDOT Northern Virginia on Twitter: @vadotnova