Provided by Virginia Department of Transportation
What’s Happening
As weather conditions allow, crews will continue corridor-wide roadway maintenance and address issues as needed, with daily multi-lane closures during daytime and overnight hours on I-66 East and West. Additional activities include:
- Constructing bridge foundations at I-495, Route 28, and Route 234 Business interchanges and Bull Run Drive overpass
- Constructing retaining walls along I-66 and Route 28
- Clearing trees and brush, grading, and drainage installation throughout the corridor
- Grading and installing drainage at the future Gainesville/University Boulevard Park and Ride Lot and Manassas/Balls Ford Road Park and Ride Lot
- Grading and excavating for the new E.C. Lawrence Park Access Road and temporary realignment of Braddock Road
- Relocating underground and overhead utilities along I-66 and Route 28
Upcoming Lane Closures and Traffic Changes
ROUTE 29 / GAINESVILLE: No significant traffic impacts scheduled.
ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS: No significant traffic impacts scheduled.
ROUTE 28 (SULLY ROAD) / CENTREVILLE: No significant traffic impacts scheduled.
ROUTE 286 (FAIRFAX COUNTY PARKWAY): I-66 West from Jermantown Road to Monument Drive Monday, April 22, through Wednesday, April 24: 9:00 p. m. to 5:00 a. m. Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.
I-66 East from Monument Drive to Jermantown Road: Thursday, April 25: 9:00 p. m. to 5:00 a. m., Friday, April 26, and Saturday, April 27: 9:00 p. m. to 9:00 a. m. Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.
ROUTE 50 / FAIRFAX: I-66 West from Jermantown Road to Monument Drive: Monday, April 22, through Wednesday, April 24: 9:00 p. m. to 5:00 a. m.Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.
I-66 East from Monument Drive to Jermantown Road: Thursday, April 25: 9:00 p. m. to 5:00 a. m., Friday, April 26, and Saturday, April 27: 9:00 p. m. to 9:00 a. m.Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.
ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX: Ramp from I-66 West to Route 123: Monday, April 22, through Saturday, April 27: 12:00 Midnight to 4:00 a. m. The ramp will be closed for underground utility relocation and other construction activities. Traffic will be detoured farther west to Route 50 East, use the left exit for I-66 East, then follow signs to Route 123 North or South.
ROUTE 243 (NUTLEY STREET) / VIENNA: No significant traffic impacts scheduled.
I-495 (CAPITAL BELTWAY): No significant traffic impacts scheduled.