Provided by Virginia Department of Transportation (VDOT)
What’s Happening
Transform 66 Outside the Beltway Project construction continues throughout the corridor during daytime and overnight hours as weather conditions allow. Current activities include:
- Bridge demolition at Route 29 in Centreville
- Constructing bridge foundations at Compton Road, Route 28, Route 123, Vaden Drive, and I-495
- Small charge dynamite operations along I-66 East and West near Route 28
- Bridge deck work for new collector-distributor road over Route 234 Business (Sudley Road) and new Route 28 bridges over I-66
- Relocating water lines at Jermantown Road, Stringfellow Road, and Gallows Road
- Constructing new utility duct bank and relocating underground utilities along I-66 East
- Constructing retaining walls along I-66 and Route 28
- Corridor-wide roadway maintenance as needed
Upcoming Lane Closures and Traffic Changes
The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.
ROUTE 29 / GAINESVILLE
No significant traffic impacts scheduled.
ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS
I-66 East and West between Sudley Road and Bull Run Rest Area
Ramps from Sudley Road to I-66 East
Tuesday, Jan. 21, through Friday, Jan. 24: 11:00 a.m. to 12:00 noon
Temporary 15-minute stoppages of traffic on I-66 East and West for blasting operations. Additionally, stoppages will occur on the ramp from Sudley Road to I-66 East. Stoppages may also be needed on Vandor Lane.
ROUTE 28 (SULLY ROAD) / CENTREVILLE
I-66 East and West between Route 29 Centreville and Stringfellow Road
Route 28 North and South between Route 29 and Braddock Road
Ramp from Route 28 North to I-66 East
Tuesday, Jan. 21, through Friday, Jan. 24: 11:00 a.m. to 12:00 noon
Temporary 15-minute stoppages of traffic on I-66 East and West, and Route 28 North and South for blasting operations. Additionally, stoppages will occur on the ramp from Route 28 North to I-66 East and on the ramp from Route 28 North to I-66 West.
Route 29 Centreville North and South at I-66
Sunday, Jan. 19: 10:00 p.m. to 5:00 a.m.
Tuesday, Jan. 21, and Wednesday, Jan. 22: 8:00 p.m. to 5:00 a.m.
The left lane will be closed on northbound and southbound Route 29 at I-66 for bridge demolition activities.
I-66 West from Route 28 to Route 29 Centreville
Ramp from I-66 West to Route 29 Centreville
Tuesday, Jan. 21: 9:30 p.m. to 6:00 a.m.
Two lanes will be closed for overhead cantilever sign removal. Additionally, the ramp from I-66 West to Route 29 Centreville will be closed from 12:00 midnight to 4:00 a.m. Drivers will be directed prior to the closure to Route 28 South, then follow signs to Route 29 North or South.
Route 28 South from Westfields Boulevard to Braddock Road
Tuesday, Jan. 21: 9:00 p.m. to 5:00 a.m.
Two lanes will be closed for overhead cantilever sign removal.
I-66 East from Compton Road to Route 29 Centreville
Wednesday, Jan. 22: 9:00 p.m. to 5:00 a.m.
Three lanes will be closed for overhead gantry removal. Drivers should expect periodic 20-minute stoppages between 12:00 midnight and 4:00 a.m.
Ramp from Route 29 Centreville South to I-66 East
Thursday, Jan 23: 12:00 Midnight to 4:00 a.m.
The ramp will be closed for utility work. Drivers will be directed farther south to Stone Road, make a U-turn onto Route 29 North and follow signs to Route 28 North, then stay to the right and follow signs to I-66 East.
ROUTE 286 (FAIRFAX COUNTY PARKWAY) / FAIR LAKES
Stringfellow Road between Fair Lakes Boulevard and Village Square Drive
Wednesday, Jan. 22, through Friday, Jan. 24: 9:00 p.m. to 3:00 p.m.
Friday, Jan. 24, from 9:00 p.m. until 3:00 p.m. Monday, Jan. 27
The right lane of southbound Stringfellow Road will be closed for underground utility relocation. The lane will be reopened weekdays between 3:00 and 9:00 p.m. to accommodate the evening rush.
ROUTE 50 / FAIRFAX
No significant traffic impacts scheduled.
ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX
Ramp from I-66 West to Route 123 (Chain Bridge Road)
Tuesday, Jan. 21: 12:00 Midnight to 4:00 a.m.
The ramp will be closed for utility work. Traffic will be detoured farther west to Route 50 East, stay to the left for I-66 East, then follow signs to Route 123.
ROUTE 243 (NUTLEY STREET) / VIENNA
No significant traffic impacts scheduled.
I-495 (CAPITAL BELTWAY) / DUNN LORING
No significant traffic impacts scheduled.
Commuter Alternatives
VDOT and the project team have invested in a broad range of programs to help commuters and others stay mobile and safe during construction. Learn more about carpool, vanpool, telework, and commuter bus alternatives.