I-66 Lane Closures and Traffic Changes, Week of July 21

Google+ Pinterest LinkedIn Tumblr +

Provided by Virginia Department of Transportation (VDOT)

What’s Happening

Project construction continues throughout the corridor during daytime and overnight hours as weather conditions allow. Current activities include:
  • Constructing bridge foundations at I-495, Route 28, and Route 234 Business interchanges, and Bull Run Drive overpass
  • Constructing retaining walls along I-66 and Route 28
  • Demolishing of structures
  • Small charge blasting operations at the Route 28 interchange
  • Clearing trees and brush, grading, and installing drainage throughout the corridor
  • Demolishing closed ramps at Route 123 Interchange
  • Grading and installing drainage at the future park and ride lots at University Boulevard (Gainesville) and Balls Ford Road (Manassas)
  • Grading and excavating for the new E.C. Lawrence Park Access Road
  • Paving of temporary realignment of Braddock Road
  • Relocating underground and overhead utilities along I-66 and Route 28
  • Corridor-wide roadway maintenance as needed

Upcoming Lane Closures and Traffic Changes

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.
ROUTE 29 / GAINESVILLE
No significant traffic impacts scheduled.
ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS
I-66 West from Compton Road to Bull Run Rest Area
Friday, July 26, and Saturday, July 27: 9:00 p. m. to 9:00 a. m.
Three right lanes will be closed for crews to mobilize a crane for upcoming bridge work at Bull Run Drive. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66.
ROUTE 28 (SULLY ROAD) / CENTREVILLE
Route 28 North at ramp to I-66 East
Route 28 South at Braddock Road
Ramps from I-66 West to Route 28 North and South
Turn lanes from Route 28 North and South to Braddock Road
Braddock Road at Newton Patent Drive
Monday, July 22, through Friday, July 26: 11:00 a. m. to 12:00 noon
Temporary stoppages of up to 15 minutes between 11:00 a. m. and 12:00 noon on Route 28 North and South at the I-66 interchange, and on Braddock Road at Newton Patent Drive for small charge blasting at the I-66/Route 28 Interchange. Additionally, the ramps from I-66 West to Route 28 North and South will be temporarily closed for up to 15 minutes beginning at 11:00 a. m.
Route 28 North from Route 29 to north of Braddock Road
Route 28 South from E.C. Lawrence Park to I-66
Braddock Road from Newton Patent Drive to Route 28
Thursday, July 25: 9:00 p. m. to 5:00 a. m.
Two lanes will be closed on Route 28 North and South with a flagging operation on Braddock Road to implement a traffic shift for the temporary alignment of Braddock Road. Drivers should expect occasional 20-minute stoppages and slowdowns along Route 28 and Braddock Road.
ROUTE 286 (FAIRFAX COUNTY PARKWAY)
No significant traffic impacts scheduled.
ROUTE 50 / FAIRFAX
No significant traffic impacts scheduled.
ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX
No significant traffic impacts scheduled.
ROUTE 243 (NUTLEY STREET) / VIENNA
No significant traffic impacts scheduled.
I-495 (CAPITAL BELTWAY)
No significant traffic impacts scheduled.