I-66 Lane Closures and Traffic Changes, Week of July 7

Google+ Pinterest LinkedIn Tumblr +

Provided by Virginia Department of Transportation (VDOT)

What’s Happening

Project construction continues throughout the corridor during daytime and overnight hours as weather conditions allow. Current activities include:
  • Constructing bridge foundations at I-495, Route 28, and Route 234 Business interchanges and Bull Run Drive overpass
  • Constructing retaining walls along I-66 and Route 28
  • Demolition of structures
  • Small charge dynamite operations at the Route 28 interchange
  • Clearing trees and brush, grading, and installing drainage throughout the corridor
  • Demolishing closed ramps at Route 123 interchange
  • Grading and installing drainage at the future park and ride lots at University Boulevard (Gainesville) and Balls Ford Road (Manassas)
  • Grading and excavating for the new E.C. Lawrence Park Access Road and temporary realignment of Braddock Road
  • Relocating underground and overhead utilities along I-66 and Route 28
  • Corridor-wide roadway maintenance as needed

Upcoming Lane Closures and Traffic Changes

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

No significant traffic impacts scheduled.
ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS
No significant traffic impacts scheduled.
ROUTE 28 (SULLY ROAD) / CENTREVILLE
Ramp from I-66 East to Route 29/Centreville
Tuesday, July 9: 12:00 Midnight to 4:00 a. m.
Temporary closure of the ramp. Traffic will be detoured to the exit for Route 286 (Fairfax County Parkway) North, then stay to the right to follow signs to I-66 West back to Route 29/Centreville.
Route 28 North at ramp to I-66 East
Route 28 South at Braddock Road
Ramps from I-66 West to Route 28 North and South
Turn lanes from Route 28 North and South to Braddock Road
Braddock Road at Newton Patent Drive 
Monday, July 8 – Friday, July 12: 11:00 a. m. to 12:00 noon
Temporary stoppages of up to 15 minutes between 11:00 a. m. and 12:00noon on Route 28 North and South for small charge blasting. Additionally, the ramps from westbound I-66 to Route 28 North and South will be temporarily closed for up to 15 minutes beginning at 11:00 a. m.
I-66 East and West at Route 28
Wednesday, July 10: 11:00 p. m. to 4:00 a. m. (Rain date: Thursday, July 11)
Multiple stoppages of up to 15 minutes in both directions simultaneously for utility work by Dominion Energy.
ROUTE 286 (FAIRFAX COUNTY PARKWAY)
No significant traffic impacts scheduled.
ROUTE 50 / FAIRFAX
No significant traffic impacts scheduled.
ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX
No significant traffic impacts scheduled.
ROUTE 243 (NUTLEY STREET) / VIENNA
No significant traffic impacts scheduled.
I-495 (CAPITAL BELTWAY)
No significant traffic impacts scheduled.

Commuter Alternatives

VDOT and the project team have invested in a broad range of programs to help commuters and others stay mobile and safe during construction. Learn more about carpool, vanpool, telework, and commuter bus alternatives.