I-66 Lane Closures and Traffic Changes, Week of March 3

Google+ Pinterest LinkedIn Tumblr +

Provided by Virginia Department of Transportation (VDOT)

Planned lane closures and traffic changes on I-66 outside the Beltway for the week of March 3 are listed below.

What’s Happening

As weather conditions allow, crews will continue corridor-wide roadway maintenance and address pavement issues as needed, with daily multi-lane closures during daytime and overnight hours on I-66 East and West. Additional activities to include:
  • Constructing bridge foundations at I-495, Route 28, Bull Run Drive, and Route 234 Business
  • Constructing pedestrian box culverts inside the Route 123 Interchange
  • Constructing retaining walls along I-66
  • Clearing trees and brush, grading, and drainage installation at the Route 28, Route 123, Route 50, and I-495 interchanges, and other work zone locations along the corridor
  • Clearing trees and brush at the future Balls Ford Park and Ride Lot near Manassas
  • Grading, drainage installation, and small charge blasting for storm drain trenches at the future University Boulevard Park and Ride Lot
  • Grading and excavating for the new E.C. Lawrence Park Access Road
  • Relocating underground and overhead utilities along I-66 and Route 28

Upcoming Lane Closures and Traffic Changes

The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE

Route 29 North and South between Heathcote Boulevard and University Boulevard
  • Wednesday, March 6: 11:00 a. m. to 12:00 Noon
  • Friday, March 8: 11 a. m. to 12:00 Noon
  • Traffic will be temporarily stopped for up to 15 minutes for small charge blasting operations at the future park and ride lot. Additionally, the ramp from I-66 West to Route 29 North (Exit 43B) will be temporarily closed for 15 minutes beginning at 11:00 a. m.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS

  • No significant traffic impacts scheduled.

ROUTE 28 (SULLY ROAD) / CENTREVILLE

  • No significant traffic impacts scheduled.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)

  • No significant traffic impacts scheduled.

ROUTE 50 / FAIRFAX

  • Ramp from Route 50 West to I-66 West
  • Tuesday, March 5: 12:00 Midnight – 4:00 a. m.
  • Temporary closure of the ramp. Traffic will be detoured farther west to Route 608 (West Ox Road) South, stay to the right for eastbound Route 50, then follow signs to I-66 West.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX

  • No significant traffic impacts scheduled.

ROUTE 243 (NUTLEY STREET) / VIENNA

  • No significant traffic impacts scheduled.

I-495 (CAPITAL BELTWAY)

  • No significant traffic impacts scheduled.