The traffic changes and lane closures scheduled on I-66 this week are listed below.
What’s Happening
Crews will continue shifting travel lanes and setting up concrete barriers to create safe work zones along Interstate 66. Upcoming planned construction activities include:
- Grading, excavating, and clearing trees and brush at the Route 28, Route 123 and Route 50 interchanges and other places where work zones are set up along the corridor
- Begin excavation for retaining walls near Jermantown Road
- Rubblizing the shoulder along eastbound I-66 in the vicinity of Route 28
- Continued grading and drainage work at the future University Boulevard Park and Ride Lot
- Begin grading and excavating for the new E.C. Lawrence Park Access Road
- Continued relocation of underground and overhead utilities along I-66
Upcoming Lane Closures and Traffic Changes
The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia 511 app.
ROUTE 29 / GAINESVILLE
No significant traffic impacts scheduled.
ROUTE 234 (SUDLEY ROAD) / MANASSAS
I-66 East from Groveton Road to Bull Run
Tuesday, Oct. 16 – Thursday, Oct. 18: 8:00 p. m. to 5:00 a. m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect occasional 15-minute full stoppages of traffic after midnight.
ROUTE 28 (SULLY ROAD) / CENTREVILLE
I-66 West from Compton Road to Bull Run
Monday, Oct. 15: 9:00 p. m. to 6:00 a .m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect intermittent 15-minute full stoppages of traffic after midnight.
I-66 East from Route 29 Centreville to Stringfellow Road
Monday, Oct. 15: 8:00 p. m. to 5:00 a .m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect occasional 15-minute full stoppages of traffic after midnight.
I-66 East from Route 28 to Fairfax County Parkway
Tuesday, Oct. 16 – Thursday, Oct. 18: 8:00 p. m. to 5:00 a. m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect occasional 15-minute full stoppages of traffic after midnight.
ROUTE 286 (FAIRFAX COUNTY PARKWAY)
I-66 East from Route 28 to Fairfax County Parkway
Tuesday, Oct. 16 – Thursday, Oct. 18: 8:00 p. m. to 5:00 a. m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect occasional 15-minute full stoppages of traffic after midnight.
I-66 West from Route 50 to Stringfellow Road
Friday, Oct. 19: 9:00 p. m. to 9:00 a. m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect intermittent 15-minute full stoppages of traffic after midnight.
ROUTE 50 / FAIRFAX
I-66 West from Route 50 to Stringfellow Road
Friday, Oct. 19: 9:00 p. m. to 6:00 a. m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect occasional 15-minute full stoppages of traffic after midnight.
I-66 East from Jermantown Road to Blake Lane
Thursday, Oct. 18: 9:00 p. m. to 5:00 a. m.
Friday, Oct. 19: 9:00 p. m. to 9:00 a. m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect occasional 15-minute full stoppages of traffic after midnight.
ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX
I-66 West from Route 243 (Nutley Street) to Route 123 (Chain Bridge Road)
Sunday, Oct. 14 – Wednesday, Oct. 17: 9:30 p. m. to 5:00 a. m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect intermittent 15-minute full stoppages of traffic after midnight.
I-66 East from Jermantown Road to Blake Lane
Thursday, Oct. 18: 9:00 p. m. to 5:00 a. m.
Friday, Oct. 19: 9:00 p. m. to 9:00 a. m.
Three left lanes will be closed to implement long-term lane shifts. Drivers should expect occasional 15-minute full stoppages of traffic after midnight.
Commuter Alternatives